Burr 8 Lateral
Milestone installed 10,854 feet of 8″ welded steel pipe. Milestone’s main challenge on this project was the designed pipeline route. We completed a pre-job walk with the Construction Manager over the project to discuss potential re-route and access prior to mobilization. We were able to make some changes to the design and re-route the project so it would be cost efficient to complete.