Cushing Meter Station

Milestone constructed a meter station including foundations, setting equipment (including meter, filter, and Remote Terminal Unit (RTU) building), pipe installation and hydrotesting, electrical and instrumentation, perimeter fence and gate installation, and fine grading and rock placement. 

Milestone self-performed concrete foundations, pipe fabrication and installation of all piping, large equipment, and valves. A crane subcontractor was utilized to set the meter skid including dual 4″ Coriolis meters and all 6″ piping. An electrical subcontractor performed all electrical work and a fencing subcontractor installed the perimeter chain link fence. Milestone coordinated construction activities with all subcontractors to ensure all work was able to be performed as planned with no conflicts.